• Best Way Concrete 206-504-2372

    Best Way Concrete 206-504-2372

    206-504-2372....Best Way Concrete Delivery and Pumping .... Short Load Concrete Delivery Call us to discuss your concrete project. Bestway concrete made fresh on site. Ideal for small volume or specialty concrete Read More
  • Best Way Concrete 206-504-2372

    We are booked through the end of the month.  Only call if you need concrete on or after May 1. 206-504-2372....Best Way Concrete Delivery and Pumping .... Short Load Concrete Delivery Read More
  • Best Way is Less Expensive

    Best Way is Less Expensive

    206-504-2372 .... Best Way Concrete .... Short Load Concrete.... Less expensive than the cost of concrete at the home improvement store and mixing yourself. Call us to discuss your project.  Call now Read More
  • Mobile Mix Process

    Mobile Mix Process

    206-504-2372....Best Way Concrete....Short Load Concrete.... Concrete is made on-site, by the truck as you need. Call us to discuss your project. Read More
  • No Wasted Concrete

    No Wasted Concrete

    206-504-2372....Best Way Concrete.... No Wasted Concrete.... Concrete is made on-site, only as much as you need. No wasted concrete to dispose of. Call us to discuss your project.  Read More
  • Typical Jobs

    Typical Jobs

    206-504-2372....Best Way Concrete.... Typical Concrete Delivery Jobs.... Best Way Concrete is ideal for patios, hot tub pads, retaining walls, deck footings, sidewalks and more. Call us to discuss your project.  Read More
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6

The big problems with placing gravel road base over utility repairs under road ways it that the gravel will eventually settle no matter how much compaction you do.  The solution it to place flow fill over the utility work done under existing roads.  Flow fill is hard enough that it will never settle.  It is also excavatable if it ever needs to be.  Because flow fill never settles, the overall costs for the project will be lower.  The job will never need to be redone.

Here the utility trench has been partially filled with sand.  We are now starting to pour flow fill over the top of the sand and under the road surface.

The second photo shows the trench has been fully filled up to the road surface level. This section of the road will never settle.

flowfill under roadway being poured 400 533

Here the utility trench has been fully filled up to the road surface level. This section of the road will never settle.

The other benefits include no workers in the trench improving safety.  No compaction equipment in the trench with greatly lowers the cost of the job.